FlexDeploy Evaluation Template

Objective

Create an actionable plan which allows users to evaluate FlexDeploy within 4 weeks.  The important aspects of this plan include a clearly defined scope, assigned resources, defined success criteria, regular checkpoints, and support from Flexagon along the way.  Flexagon's process to enable evaluators to achieve this objective is summarized as follows:

  • Develop an evaluation plan

    • Current state assessment & future state planning

    • Define scope (technologies and use cases)

    • Determine customer resources required to meet objectives over a 4 week period

    • Create a simple project plan to make the objectives actionable and achievable

  • Flexagon will provide consulting for the first two weeks (six 2 hour working sessions)

  • Weekly review of progress and issues with customer implementation and leadership teams, and Flexagon sales and consulting teams.

  • Email support for the remaining two weeks of the evaluation period

  • Support in creating the presentation, demo, and business case to key stakeholders and decision makers

  • Final review and definition of any next steps

The evaluation planning, working sessions, support, and assistance in preparing the business case are available at no cost.

Assumptions

  • Evaluation will be executed over 4 contiguous weeks.

  • Customer will provide resources required to carry out the defined scope within the evaluation period.

  • FlexDeploy installation (including any supporting software) will be completed prior to the start of the evaluation period.

  • The pre-evaluation checklist is completed prior to the start of the evaluation period.

Deliverables

  • Evaluation Plan

  • Execution of Use Cases per evaluation plan

  • Meeting minutes of each checkpoint

  • Presentation/Demo/Business Case

Pre-Evaluation Checklist

  • Is there budget for purchase provided evaluation is successful and business case can be made?

  • Is there a clearly defined scope?

  • Are all use cases documented?

  • Is FlexDeploy installation complete?

  • Are sufficient and appropriate resources allocated to complete the POC scope during the evaluation period?

  • Has all the requested supporting information been collected (e.g. environment/server details)?  See Preparation for FlexDeploy POC.

  • Have working sessions been scheduled?

  • Have checkpoint meetings been scheduled?

Scope

The Evaluation Planning will define the scope of the evaluation:

  • Technologies

  • Future State Definition

  • SCM Integration

  • External tools such as Jira or ServiceNow

  • Enviornments & Instances participating in the pipeline

Use Cases

Specific use case to be carried out (including pipeline and release).

Evaluation Project Plan

See sample project plan for 4 week evaluation.

  File Modified

Resources

Estimated resources required for the evaluation.  Week zero is in the two weeks leading up to the start of the evaluation.

Week 0 - Evaluation Planning / Pre-Evaluation Checklist

Role

Resource Name

Hours Expectation

Role

Resource Name

Hours Expectation

Flexagon Consultant



2

Customer Technical Lead



2-5 (based on scope)

Customer Administrator



2-5 (based on scope)

Customer Project Sponsor



1

Week 1 - FlexDeploy Configuration & Hands-on Training

Role

Resource Name

Hours Expectation

Role

Resource Name

Hours Expectation

Flexagon Consultant



6

Customer Technical Lead



12-20 (based on scope)

Customer Administrator



3-5 (based on scope)

Customer Project Sponsor



0.5

Week 2 - FlexDeploy Execution & Use Case Execution

Role

Resource Name

Hours Expectation

Role

Resource Name

Hours Expectation

Flexagon Consultant



6

Customer Technical Lead



12-20 (based on scope)

Customer Administrator



1-3 (based on scope, as needed)

Customer Project Sponsor



0.5

Week 3 - Execute Use Cases contd.

Role

Resource Name

Hours Expectation

Role

Resource Name

Hours Expectation

Flexagon Consultant



2 (email support)

Customer Technical Lead



10-20 (based on scope)

Customer Administrator



1-3 (based on scope, as needed)

Customer Project Sponsor



0.5

Week 4 - Prepare demo, presentation & business case

Role

Resource Name

Hours Expectation

Role

Resource Name

Hours Expectation

Flexagon Consultant



1-2

Customer Technical Lead



2-4 (based on scope)

Customer Administrator



1-3 (as needed)

Customer Project Sponsor



1-2

Meetings

  • Evaluation Planning (1 hour)

  • Checkpoint #1 (30 minutes)

  • Checkpoint #2 (30 minutes)

  • Checkpoint #3 (30 minutes)

  • Presentation/Demo/Business Case Preparation (1 hour)