A pipeline is a workflow which orchestrates the delivery of snapshots across the stages/environments.  While a deploy workflow defines the implementation for the delivery of a single build artifact into an environment, the pipeline operates at a higher level, and orchestrates the propagation of many deployments across many stages/environments. The pipeline includes facilities for approvals, manual tasks, scheduling, deployments, and much more.


A sample pipeline definition with three stages:

Image Modified

The pipeline above has three stages, Development, QA, and Production.  The Development stage does not have any gates, which means the steps begin execution immediately.  The "Deploy All Projects" step deploys all of the project versions in a snapshot into the Development environment, which utilizes the deploy workflows of the underlying projects to facilitate this work. The QA stage has three gates.  The "Dev Quality Check" gate verifies that tests for the projects in the snapshot in Development meet the configured qualifier metrics.  If the qualifier metrics did not pass then the gate fails, otherwise, the gate completes and it transitions to the next gate.  The "QA Manager Approval" gate creates an approval task for the QA Manager group and blocks execution until approved.  Once approved, the "Every Day at Noon" scheduled gate blocks execution until 12pm. When the schedule is reached, the "Deploy All Projects" step for QA is executed.  When the deployment is complete, the pipeline execution transitions to the Production stage and executes its gates and steps (similar to QA). 

In a typical release, most of the snapshots will not make it very far through the pipeline.  The approval gates are either rejected, or they the snapshot is simply "out dated" by a newer one.  Depending on the size and complexity of a release, there may be dozens or even hundreds of iterations in the lower stages before the first snapshot is promoted to the later stages.  In fact, it is possible that only one snapshot for the release ultimately makes its way all the way to production.  At such time, the release may be ended, and a new one is created.  However, if desired, the same release can be used to deliver additional fixes or updates.


Gate Types

Type

Description

Approval

Creates an approval task for the defined group, and blocks transition until the task is approved.  If the task is rejected, the stage execution is marked as failed, and execution is terminated.

External ApprovalCreates an approval task tied to an external system (e.g. ServiceNow), and blocks transition until the task is approved.  If the task is rejected, the stage execution is marked as failed, and execution is terminated.

Schedule

Blocks transition until the defined schedule is reached, or overridden by a user with appropriate privileges.

Test

Evaluates the test qualifiers for any tests which were executed for the same snapshot in the configured environment.  The gate is successful if the qualifiers determine success, or fails otherwise.

...